Parametric estimates are based on variables such as:

Parametric estimates are based on variables such as:

A.

Project objectives and manpower allocations.

B.

Physical characteristics and historical data.

C.

Precise measurements and multiple inputs.

D.

The WBS and similar projects.

E.

Detailed planning and cost restraints.