BCS ISEB-PM1 Question Answer
Which of the following is NOT a reason to measure variances from the baseline?
To catch deviations early
To allow early corrective action
To determine if there are any wild fluctuations
To create a project control system
TESTED 15 Oct 2025
Copyright © 2014-2025 ACE4Sure. All Rights Reserved