In which of the following is the cost of risk hidden by the contractor?
Fixed Price Plus Incentive
Firm Fixed Price Contract and Fixed Price Plus Incentive
Firm Fixed Price Contract
Cost Plus Percentage of Cost
Cost Plus Fixed Price