An activity that consumes no time or resources and shows only that a dependency exists...

An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:

A.

A milestone

B.

A dummy activity

C.

Both 1) A milestone and 2) A dummy activity

D.

A hammock