A project has seven activities: A, B, C, D, E, F, and G.

A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed.

Which activities have float available?

A.

Activity A has two weeks’ float, activity F has one week.

B.

Activity F has one-week float.

C.

There is no float available in the project.

D.

Activity A has eight weeks’ float.

ISEB-PM1 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now ISEB-PM1 pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"