Which of the following is the PRIMARY benefit of project governance?
A.
Projects considered essential are prioritized over others already in progress.
B.
Business projects need less monitoring, which allows local managers freedom to execute their projects.
C.
Projects that are behind targets may be allowed to continue, if the cause of the delay can be resolved.
D.
Business cases and associated benefits are subject to effective scrutiny, which helps with setting project timelines.
The Answer Is:
D
This question includes an explanation.
Explanation:
The primary benefit of project governance is the structured evaluation of business cases, ensuring that projects align with strategic objectives. This scrutiny helps prioritize projects, allocate resources effectively, and set realistic timelines. By critically assessing the potential benefits and risks, organizations can ensure that projects deliver value and meet stakeholders' expectations, facilitating better decision-making and accountability in project management.
INTE PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"