A manufacturing firm prepares the following materials requirement plan (MRP):Master Production ScheduleWeek123456Item A101015152020Relevant InformationItemItem's ParentItem's...

A manufacturing firm prepares the following materials requirement plan (MRP):

Master Production Schedule

Week123456

Item A101015152020

Relevant Information

ItemItem's ParentItem's Lead TimeItem's Lot SizeItem's Current Inventory

ANone1 weekLFL50

BA2 weeks5010

CB2 weeks5010

Using MRP methodology, how much of Item B should be ordered, and when should it be ordered7

A.

50 items immediately and 50 items in week 3

B.

20 items in week 4 and 20 items in week 5

C.

10 items in week 2 and 20 items in week 3

D.

50 items in week 2

INTE PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now INTE pdf
Get 75% Discount on All Products, Use Coupon: "ac75sure"