A manufacturing firm is preparing a materials requirement plan for the next six weeks. The information is as follows:
Master Production Schedule
Week123456
Item A51015202530
Other Relevant Information
ItemItem's ParentItem's Lead TimeItem's Lot SizeItem's Current Inventory
ANone1 weekLFL20
BA2 weeks105
CB3 weeks205
How many levels does the product structure have in the bill of materials?