A firm completes its near level production, five-month demand plan for the next business planning...

A firm completes its near level production, five-month demand plan for the next business planning cycle:

Month 1Month 2Month 3Month 4Month 5

Demand Forecast15,00020,00025,00025,00018,000

Production Plan (Regular Time)20,00020,00020,00020,00018,000

Production Plan (Overtime)5,000

Ending Inventory5,0005,000

Average Inventory2,5005,0002,500

Workforce PlanningStarting WorkforceMonth 1Month 2Month 3Month 4Month 5

Hires7

Layoffs2

Actual Workforce Size132020202018

Regular Time Hours Required2,0002,0002,0002,0001,800

Overtime Hours Required500

Costs

Regular time cost per unit$15

Overtime cost per unitS25

Monthly inventory cost per unit$1

Cost of hire$1,500

Cost of layoffS400

What is the cost of this demand plan?

A.

$1,605,000

B.

$180,800

C.

$1,606,300

D.

$1,616,300

INTE PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now INTE pdf
Get 75% Discount on All Products, Use Coupon: "ac75sure"