The correct answers are A and D because the Quality Analyst team contributes to project quality both early in the lifecycle and later during formal validation activities .
D. Participating in Story Huddles with analysts and developers to understand the requirements is correct because quality begins well before formal testing starts. In Guidewire projects, Quality Analysts play an important role in understanding stories, clarifying expected behavior, identifying gaps or ambiguities, and preparing for effective test design. Their involvement in story discussions helps ensure that requirements are testable and that potential defects are prevented earlier rather than only detected later.
A. During the Stabilization phase, to conduct end-to-end testing, performance testing, and support User Acceptance Testing (UAT) is also correct because Stabilization is the phase where the integrated solution is validated more comprehensively. Quality Analysts are central to coordinating and executing testing efforts that confirm the system works across business flows, performs adequately, and is ready for business acceptance and release.
The other options are not the best choices. B is incorrect because QA is not involved only at launch, and direct end-user support is not their exclusive core responsibility. C relates more to project governance and organizational setup than QA execution. E describes configuration work typically performed by developers or configurators, not Quality Analysts. F refers more to cloud compliance and standards oversight rather than the primary QA role.
So, in Guidewire Cloud implementations, Quality Analysts are especially critical in Story Huddles and during the Stabilization phase .