In Agile Scrum, a sprint typically lasts two to four weeks. This time-boxed iteration balances being long enough to deliver meaningful work but short enough to allow flexibility and frequent feedback.
Option B: One to two months is too long for a sprint cycle.
Option C: A sprint ends at its time-box, not “until goals are completed.”
Option D: Three to six weeks exceeds the recommended sprint length.
Thus, the typical sprint length is two to four weeks.