As a team member you are frustrated that a product backlog increment was considered finished without validating it met the conditions of satisfaction. Defects are piling up and team morale is suffering. In what forum should this issue be addressed?

A.

One on one with manager

B.

Retrospective

C.

Special meeting to discuss solutions

D.

Daily stand up