When there's a dispute between the contracting parties
B.
When ail contractual obligations have been discharged.
C.
When there is a force majenre.
D.
When the termination clause is enacted.
The Answer Is:
B
This question includes an explanation.
Explanation:
A contract is closed out when all the contractual terms have been fully satisfied, including the completion of deliverables, final payments, and any post-contract evaluations or obligations.
Correct Answer (B - When all contractual obligations have been discharged)
According to contract management principles and IIA standards, a contract is officially closed out once:
All agreed-upon deliverables have been completed.
All payments and financial obligations are settled.
Final performance evaluations or audits are completed.
The contract is formally reviewed and documented for closure.
The IIA’s GTAG 3: Contract Management Framework supports that contract closure occurs after full performance and obligations are met.
Why Other Options Are Incorrect:
Option A (When there's a dispute between contracting parties):
Disputes do not necessarily close out a contract; instead, they may lead to mediation, renegotiation, or legal action. The contract remains active until resolved.
The IIA’s Practice Guide: Auditing Contracts recommends dispute resolution mechanisms but does not define them as a reason for contract closure.
Option C (When there is a force majeure event):
A force majeure (unforeseen event like natural disasters or war) may suspend or modify contractual obligations but does not always lead to closure.
The contract may be renegotiated or resumed once conditions allow.
Option D (When the termination clause is enacted):
Termination and closure are not the same. Termination means ending the contract before full obligations are met, whereas closure means fulfilling all obligations.
IIA GTAG 3: Contract Management Framework explains that contract termination can occur under specific clauses, but closure happens only after all duties are fulfilled.