An internal auditor is reviewing key phases of a software development project.

An internal auditor is reviewing key phases of a software development project. Which of the following would; the auditor most likely use to measure the project team's performance related to how project tasks are completed?

A.

A balanced scorecard.

B.

A quality audit

C.

Earned value analysis.

D.

Trend analysis