A organization finalized a contract in which a vendor is expected to design, procure, and...

A organization finalized a contract in which a vendor is expected to design, procure, and construct a power substation for $3,000,000. In this scenario, the organization agreed to which of the following types of contracts?

A.

A cost-reimbursable contract.

B.

A lump-sum contract.

C.

A time and material contract.

D.

A bilateral contract.