The following is a list of major findings in the executive summary report for an...

The following is a list of major findings in the executive summary report for an audit of the contract management process

- Noncompliance with contract provisions requiring vendors to obtain insurance policies with indemnity value of not less than $1 million

- Compliance with contract obligations and deliverables is not monitored

- No contract agreement with five vendors providing core services

Which of the following is an appropriate conclusion that can be drawn from these findings?

A.

These are weaknesses resulting from a lack of a documented contracting policy

B.

Substandard service delivery by vendors may not be detected

C.

Management should expedite actions to rectify the observations identified

D.

The internal controls guiding contract management are not operating effectively

IIA-CIA-Part2 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now IIA-CIA-Part2 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"