The final engagement communication contains the following observation:
The internal auditor discovered that three of the 10 contracts reviewed failed to meet the organization ' s competitive bidding requirements Management explained that senior management deemed these purchases to be critical and awarded them as sole-source. "
Which of the following components is missing in the documentation of the observation?