According to IIA guidance which of the following statements is true regarding heat maps?
A.
A heat map sets likelihood to have higher priority than impact.
B.
A heat map sets impact to have higher priority than likelihood.
C.
A heat map recognizes that the priority of impact and likelihood can vary.
D.
A heat map recognizes impact and likelihood as equally important
The Answer Is:
C
This question includes an explanation.
Explanation:
According to IIA guidance, heat maps are tools used in risk assessment that visually represent the severity of risks by plotting them on a matrix based on their likelihood and impact. Heat maps are flexible and can be adjusted to prioritize either likelihood or impact depending on the specific context and the organization’s risk appetite and tolerance. This recognition that the priority of impact and likelihood can vary allows for a more nuanced and tailored risk assessment approach.
IIA Practice Guide: Assessing the Risk Management Process
IIA Standard 2120: Risk Management
IIA-CIA-Part2 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"