A manufacturer is under contract to produce and deliver a number of aircraft to a...

A manufacturer is under contract to produce and deliver a number of aircraft to a major airline. As part of the contract, the manufacturer is also providing training to the airline's pilots. At the time of the audit, the delivery of the aircraft had fallen substantially behind schedule while the training had already been completed. If half of the aircraft under contract have been delivered, which of the following should the internal auditor expect to be accounted for in the general ledger?

A.

Training costs allocated to the number of aircraft delivered, and the cost of actual production hours completed to date.

B.

All completed training costs, and the cost of actual production hours completed to date.

C.

Training costs allocated to the number of aircraft delivered, and 50% of contracted production costs.

D.

All completed training costs, and 50% of the contracted production costs.

IIA-CIA-Part2 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now IIA-CIA-Part2 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"