Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

At the beginning of an IT development project, key risks were identified and assessed, and...

At the beginning of an IT development project, key risks were identified and assessed, and risk owners were appointed. Six months later, the IT development team reported that the project is significantly over budget, it will not be completed on time, and key personnel had left the organization. Which of the following risk management practices should be improved for future projects?

A.

Risk response

B.

Risk assessment

C.

Risk monitoring

D.

Risk avoidance

IIA-CIA-Part1 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now IIA-CIA-Part1 pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"