IIA IIA-ACCA Question Answer
Which of the following statements is in accordance with COBIT?
1. Pervasive controls are general while detailed controls are specific.
2. Application controls are a subset of pervasive controls.
3. Implementation of software is a type of pervasive control.
4. Disaster recovery planning is a type of detailed control.