Refer to the exhibit.

Refer to the exhibit.

Interfaces 1/1/53 and 1/1/54 were accidentally disconnected from Switch-A, the primary VSX member. Client A is experiencing network disruptions with network connections to Router-A.

What needs to be done to prevent user traffic disruption in this scenario?

A.

Configure VSX shutdown on-split on SW-B.

B.

Configure keepalive VLAN on upstream lag.

C.

Configure VSX shutdown on-split on SW-A.

D.

Configure keepalive using mgmt ports between SW-A and SW-B.