Which of the following statements is correct about the division of responsibilities in a data...

Which of the following statements is correct about the division of responsibilities in a data center service migration project?

A.

During the project implementation, the project implementer is responsible for progress management, risk control quality management, subcontract management, construction management, contract change confirmation, and engineering delivery.

B.

During the project implementation, the customer must provide necessary resources to ensure power supply, refrigerating, lighting, firefighting, equipment room protection, network bandwidth, applying for contract changes, migration personnel arrangement, and so on.

C.

Common responsibilities refer to the work that requires both parties to confirm or to complete together during the project implementation.

D.

During the project implementation, the migration implementer is responsible for confirming the project progress, acceptance criteria, hardware installation environment, and device quantity.

H31-522 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now H31-522 pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"