Assuming a site data volume of 600GB, A,B site replication bandwidth between 40% of GE...

Assuming a site data volume of 600GB, A,B site replication bandwidth between 40% of GE network resources, and asynchronous remote replication synchronization. If the synchronization time is 180 minutes and begins at 9:00 AM, when will the next synchronization start?

A.

10:25

B.

12:00

C.

15:00

D.

15:20