You are the project manager of the Workstation Improvement Project for your organization.

You are the project manager of the Workstation Improvement Project for your organization. This project will replace 925 workstations with new computers for your company's employees. Mark Jones, the sales manager, has requested that your project add 250 laptops as part of this project as his employees do not have workstations as they travel as part of the sales process. Mark insists that his department in the company can pay for the cost of the laptops. All of the following are components that will be affected by this change request except for which one?

A.

There will be a need for additional time to install the laptops.

B.

There will be a need for an additional project scope statement because of the change request.

C.

There will be a need for additional procurement management processes.

D.

There will be a need for additional risk analysis for the laptops.

GSLC PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now GSLC pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"