Tim is working as a project manager for the TCH project.

Tim is working as a project manager for the TCH project. The project is in the final stages and the closing processes are being performed. He has prepared the lessons learned document. This document will be the part of ____.

A.

The project's performance record

B.

The project charter

C.

The risk register

D.

The company's organizational process assets