You are the project manager for BlueWell Inc. You are reviewing the risk register for your project. The risk register provides much information to you, the project manager and to the project team during the risk response planning. All of the following are included in the risk register except for which item?

A.

Trends in qualitative risk analysis results

B.

Symptoms and warning signs of risks

C.

List of potential risk responses

D.

Network diagram analysis of critical path activities