You work as a project manager for PassGuide Inc.

You work as a project manager for PassGuide Inc. You are working on several projects. Your projects vary in size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can compare relative schedule and cost performance of each project. Which of the following components of EVM provide measures of schedule and cost performance that are not affected by the size of the project?

A.

BAC and EAC

B.

CPI and SPI

C.

CV and SV

D.

PV and EV