You are the project manager of the NJYO Project and are working with your project team to create the Work Breakdown Structure (WBS). This project will span all areas of the matrix organization and your project team doesn't really know the resources from the other departments. Some of the project team members have asked that you excuse them from the WBS when the section of the project scope doesn't apply to them. You tell them 'No'. Why?