Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

Rick is the project manager for TTM project.

Rick is the project manager for TTM project. He is in the process of procuring services from vendors. He makes a contract with a vendor in which he precisely specify the services to be procured, and any changes to the procurement specification will increase the costs to the buyer.

Which type of contract is this?

A.

Fixed Price Incentive Fee

B.

Cost Plus Fixed Fee Contract

C.

Firm Fixed Price

D.

Fixed Price with Economic Price Adjustment

GCPM PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now GCPM pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"