Jane works as a project manager for PassGuide Inc.

Jane works as a project manager for PassGuide Inc. Various projects are running under her administration. Holly, the team leader of a project, provides Jane the performance indexes of her project. The schedule variance (SV) of her project is 15. What does this figure illustrate?

A.

Holly's project is ahead of the schedule.

B.

Holly's project is behind the schedule.

C.

Holly's project has costs that are higher than planned.

D.

Holly's project is right on target.