Jane works as a project manager for PassGuide Inc. She is calculating the estimated activity durations for her project. She is using parameters such as duration, budget, size, weight, and complexity from a previous similar project as the basis for estimating the new project. Which of the following estimate activity duration techniques is she using in the project?

A.

Expert judgment

B.

Three-point

C.

Parametric

D.

Analogous