GIAC G2700 Question Answer
You are the project manager for a construction project. The project involves casting of a column in a very narrow space. Because of the lack of space, casting is highly dangerous. High technical skill will be required for casting that column. You decide to hire a local expert team for casting that column. Which of the following types of risk response are you following?