GIAC G2700 Question Answer
Sam uses Monte Carlo simulation to quantitatively assess cost and schedule risks of his project during planning processes. During risk monitoring and control, Sam repeats the technique, but it leads to different results. Which of the following cannot be the reason for the difference in results?