An Implementation Engineer is performing a hardware NDU from a fully populated FlashArray//X90R3 to a...

An Implementation Engineer is performing a hardware NDU from a fully populated FlashArray//X90R3 to a FlashArray//XL that already contains 20 DFM-Ds. The drive transfer is complete, and the //XL is still in SPM (Shelf Personality Mode).

What is the next step the Implementation Engineer should take to continue the upgrade?

A.

Evacuate DMMs as a data pack, then install into any open slot in the //XL.

B.

Hot swap and move each DMM into any open //XL slot without evacuation.

C.

Evacuate and remove each DMM one-by-one, then set aside.

D.

Run the purehw dmm migrate command to transfer cache state to the //XL.

FlashArray-Implementation-Specialist PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now FlashArray-Implementation-Specialist pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"