CIMA E2 Question Answer
With respect to the management of quality on projects, which of the following statements is true?
The only actions required are to inspect the final deliverables and reject items that do not meet specifications.
A key responsibility of a project manager is to ensure that design specifications are met.
The central theme of project quality is to exceed the expectations of the client by building to the highest standards.
Most project processes produce outputs with no variation in quality characteristics.