Many companies use Critical Path Analysis (CPA) to manage projects.

Many companies use Critical Path Analysis (CPA) to manage projects.

 

Which TWO of the options below could be identified from a CPA diagram? 

A.

The activities which need to be completed before the next activity can start.

B.

The resource usage variance for each activity.

C.

The activities which can't overrun without delaying the whole project.

D.

The probable time for each activity.