Who decides how much is moved from the product backlog to the iteration backlog?
A.
Team members
B.
Product Owner
C.
Stakeholders
D.
Team manager
E.
Project Manager
The Answer Is:
A
This question includes an explanation.
Explanation:
In Disciplined Agile, it is the team members who decide how much work is moved from the product backlog to the iteration backlog. This decision is based on the team's capacity, velocity, and understanding of the complexity and size of the work items. While the Product Owner (B) prioritizes the product backlog, it is up to the team to determine how much of that work can be realistically completed within an iteration. Stakeholders (C), the team manager (D), or the project manager (E) do not make this decision.
[Reference: PMI’s "Disciplined Agile Senior Scrum Master (DASSM) Handbook" on iteration planning and roles in DA., , ]
DASSM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 75% Discount on All Products,
Use Coupon: "ac75sure"