What is the primary risk addressed by the stakeholder vision milestone?
A.
That your architectural strategy is likely to work
B.
That your primary stakeholders agree to your strategy
C.
That the business case for the project is viable
D.
That a release plan for the project is realistic
The Answer Is:
B
This question includes an explanation.
Explanation:
The primary risk addressed by thestakeholder vision milestoneisthat your primary stakeholders agree to your strategy. This milestone ensures alignment and consensus among key stakeholders regarding the project's overall vision, goals, and strategic approach. Achieving this agreement is critical to securing buy-in, support, and commitment from stakeholders, which helps to mitigate the risk of misalignment and conflicting expectations as the project progresses. Other risks, like architectural strategy viability, business case viability, or a realistic release plan, are addressed by other specific milestones or checkpoints in the Disciplined Agile framework.
DASSM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 75% Discount on All Products,
Use Coupon: "ac75sure"