Which artifact collects all the work flowing to the team?
A.
Business backlog
B.
Iteration backlog
C.
Product backlog
D.
Release roadmap
The Answer Is:
C
This question includes an explanation.
Explanation:
TheProduct backlogis the artifact that collects all the work flowing to the team. It contains a prioritized list of user stories, tasks, enhancements, bug fixes, and other work items that represent the overall scope of the product development effort. The Product Owner manages the backlog, ensuring it is continuously refined and updated to reflect changing priorities and requirements. The iteration backlog (option B) is a subset of the product backlog items that the team commits to delivering in a single iteration, while the business backlog and release roadmap are not typically used to collect all work items for a team.
DASSM PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 75% Discount on All Products,
Use Coupon: "ac75sure"