According to the Test Plan guidelines, how should you validate redundancy capabilities of the network during a system failure?

A.

Remove one Aggregation switch power supply

B.

Disable the primary interface on Switch-A

C.

Power off the primary ToR switch

D.

Remove one power module from ToR switch A