Which of the following best describes the risk of too many epochs on the same...

Which of the following best describes the risk of too many epochs on the same data?

A.

Unpredictability of returned outputs

B.

Insufficient monitoring of system usage

C.

Inability to perform unit testing

D.

Overfitting of the model