Which of the following is NOT a test control activity?
A.
Re-prioritize tests because of time pressure
B.
Change the test schedule due to viability of a test environment
C.
Writing test suspension and resumption criteria in the test plan
D.
Set an entry criterion requiring fixes to be retested by a developer before accepting them into a build
The Answer Is:
C
This question includes an explanation.
Explanation:
Test control is a test management activity that involves making decisions based on information from test monitoring and test progress reporting. Test control activities include:
Re-prioritizing tests because of time pressure
Changing the test schedule due to availability of a test environment
Setting entry and exit criteria for test levels or test activities
Initiating corrective actions to resolve deviations from the test plan
Writing test suspension and resumption criteria in the test plan is not a test control activity, but rather a test planning activity. Test suspension and resumption criteria are used to define when to stop and resume testing in case of unforeseen events or issues that affect the test execution.
References: Certified Tester Foundation Level Syllabus, Section 2.4.2 and 2.4.3
CTFL_Syll2018 PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"