In the last project, the usability tests substantially exceeded the budget of the test plan.

In the last project, the usability tests substantially exceeded the budget of the test plan. Which quality control task could have been used to avoid this?

A.

Check that the usability test plan has been properly reviewed

B.

Check consumed resources regularly and compare with the estimates

C.

Check that findings are communicated to the stakeholders

D.

Check whether the usability test report conforms to the best practices