Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

In the last project, the usability tests substantially exceeded the budget of the test plan.

In the last project, the usability tests substantially exceeded the budget of the test plan. Which quality control task could have been used to avoid this?

A.

Check that the usability test plan has been properly reviewed

B.

Check consumed resources regularly and compare with the estimates

C.

Check that findings are communicated to the stakeholders

D.

Check whether the usability test report conforms to the best practices

CTFL-UT PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CTFL-UT pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"