During the software development process, at what point can the test process start?
A.
When the code is complete.
B.
When the design is complete.
C.
When the software requirements have been approved.
D.
When the first code module is ready for unit testing
The Answer Is:
C
This question includes an explanation.
Explanation:
The test process can start as soon as the software requirements have been approved. The ISTQB CTFL syllabus v4.0 emphasizes that early involvement of testing helps in identifying defects early in the lifecycle, which includes the validation of requirements and planning of testing activities based on those requirements.