Which statement about an Agile task board is CORRECT?
A.
It provides detailed visual representation of the whole team's status.
B.
It is updated once at the end of each iteration.
C.
Only “in progress” tasks are shown on the task board.
D.
It is a detailed visual representation of the status of testing.
The Answer Is:
A
This question includes an explanation.
Explanation:
An Agile task board is a visual framework to display and sync up on the tasks moving between production steps. It is usually applied to the two most popular Agile development frameworks — Kanban and Scrum. Used by software developers and project managers, an Agile board helps manage workloads in a flexible, transparent, and iterative way1. An Agile task board provides a detailed visual representation of the whole team’s status, showing which tasks remain to be started, which are in progress, and which are done. It also helps to track the progress of the current sprint, identify bottlenecks, and facilitate collaboration and communication among team members2. References:
: ISTQB® Foundation Level Agile Tester Syllabus, Version 2014, Section 2.1.1