ISTQB CTAL-TM Question Answer
You are the Test Manager on a project to replace an old sales and merchandising system with one that will be based on modern platforms.
The main requirements for the system are:
Loading sales data, sent electronically from the stores each evening, into a central database.
Producing sales reports for the merchandisers.
Producing forecast reports, used to predict demand.Loading sales data and producing reports with the current system has frequently taken longer than the overnight processing window allows. The Data Centre Manager requires that all batch processing takes at least 10% less time than currently.The Sales and Merchandising Manager is more concerned about usability because the parameter entry will be complex.Which option contains two key considerations that would need to be added to your test approach?