You are monitoring the test results for the first week of system test execution to...

You are monitoring the test results for the first week of system test execution to ensure they conform to the test plan objectives. You are guided by the list of test conditions and traceability matrix produced following test design. Test Plan objectives

• Approach - Risk-based and depth first

• Status reporting - Execution statuses must be either "Passed*, "Failed", "Blocked" or "Not Run"

• Traceability - Test execution results must be traceable back to the test conditions

Test Conditions

Traceability matrix

Which one of the following is a correct statement regarding the current status of test plan objectives?

SELECT ONE OPTION

A.

All the Traceability objective has been met.

B.

All objectives have been met.

C.

None of the objectives have been met.

D.

Only Approach and Traceability objectives have been met.

CTAL-TM PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now CTAL-TM pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"