The primary benefit of using a project charter is that it
A.
ensures that the team members understand the causes of issues
B.
provides the project management tools to be used by the team
C.
ensures that stakeholders will support the project
D.
ensures the team will work to meet expectations
The Answer Is:
D
This question includes an explanation.
Explanation:
The best answer is D. ensures the team will work to meet expectations . The CSSBB source defines a project charter as a written document that defines the team’s mission, scope, objectives, time frames, and consequences. It also states that identifying these details in written form provides a constant and consistent target for the team . The charter’s listed advantages include eliminating confusion, defining boundaries, identifying deliverables, and providing a basis for team goal setting.
That means the charter’s primary benefit is to align the team around what is expected so they can work toward those defined expectations. It does not guarantee stakeholder support, nor does it provide all project management tools. It also does not ensure that team members already understand root causes, since root-cause analysis comes later. While option D is not stated word-for-word in the source, it is the closest interpretation of the charter’s function as a consistent target and expectation-setting document. Therefore, the verified best answer is D .
CSSBB PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"