A process decision program chart (PDPC) can be used to develop a
A.
project schedule
B.
cause and effect matrix
C.
tree diagram
D.
contingency plan
The Answer Is:
D
This question includes an explanation.
Explanation:
The correct answer is D. contingency plan . The CSSBB material defines the process decision program chart (PDPC) as a method used to chart the course of events from a starting point to a final complex goal, while recognizing that uncertainty in intermediate steps may derail progress. The source explicitly states that the various events are charted and contingencies are planned for , and further notes that the PDPC method is similar to contingency planning .
This makes PDPC especially valuable when the problem is new, complex, or involves challenging steps where “what-if” failures may occur. The tool helps the team anticipate risks and identify fallback actions before implementation problems arise. It is not primarily a project schedule, because scheduling is more closely associated with tools such as activity network diagrams or PERT/CPM. It is also not a cause-and-effect matrix, which is used for relating variables, nor is it a tree diagram, although both are among the management and planning tools. The PDPC extends beyond simple branching logic by planning responses to possible breakdowns. Therefore, from a CSSBB standpoint, the best answer is D. contingency plan .
CSSBB PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"